Skip to content
Back to case studies

Project Coordination

Annual in-suite HVAC maintenance across 300 units

Technician servicing an in-suite fan coil unit in a condominium suite
Role
Project Coordinator (Condo Administrator)
Timeline
Annual project · 5-day delivery window

Overview

Coordinated the building’s annual in-suite fan coil filter replacement and HVAC maintenance program for a 300-unit residential condominium in downtown Toronto. Suite entry was required in every home, so the project depended on budget approval, clear communication with 600+ residents, controlled access, and close daily tracking with the HVAC vendor to finish within a five-day window. Every unit that couldn’t be accessed as scheduled meant a return visit costing the corporation more than $200 in vendor charges plus a two-hour minimum for a security escort, so first-time access was the main driver of cost and schedule.

Project at a Glance

Scope
300 suites, 600+ residents
Schedule
5 days, ~60 units (five floors) a day
Daily crew
2 vendor technicians + 1 security escort
Cost of a missed unit
$200+ per return visit (2-hour minimum at $120/hr plus travel and materials), plus a security escort at a 2-hour minimum ($28/hr + tax)

Project Goals

  • Make sure all 600+ residents knew the suite-entry schedule and how to prepare
  • Complete the work in all 300 units within five days
  • Track progress daily and keep the project on schedule
  • Keep regular communication with the HVAC company’s Project Manager
  • Identify and resolve issues or delays as quickly as possible

Key Activities

  • Obtained the work order and quotation from the vendor, reviewed costs against the corporation’s approved budget, and secured approval from the Property Manager and Board Treasurer
  • Built the schedule around daily capacity: two technicians and one security escort completing about 60 units (five floors) a day
  • Sent electronic suite-entry notices to all residents with a preparation checklist (clear access to fan coil units, arrange care for pets)
  • Posted hard-copy notices in the elevators, mailroom, lobby and front desk so every resident received the information
  • Arranged security escorts for technicians entering suites when residents were not home, following the building’s access procedures
  • Tracked daily progress with the HVAC Project Manager: technicians on site, floors and units completed, and units that could not be accessed
  • Logged every access issue and its cause (resident illness, blocked units, locks changed without notifying Management) for follow-up and future planning
  • Minimized return visits, each costing $200+ in vendor charges plus a two-hour minimum security escort, through clear preparation checklists and early follow-up with residents
  • Grouped any return visits (up to five a day) to make the best use of vendor and security time
  • Stated in resident notices that residents who changed their locks must provide access, so the corporation didn’t pay the $260-per-unit cost of a contractor lock change
  • Obtained the final report from the HVAC Project Manager and documented outstanding deficiencies and units needing return visits

Outcomes

  • All 300 units completed within the planned five-day schedule (~60 units a day)
  • 600+ residents informed through digital and physical notices, with minimal disruption
  • Fewer than 10 of 300 units needed a return visit (about 97% completed on the first visit), avoiding $200+ in vendor costs plus security time for each unit accessed the first time
  • Locked-suite access handled under resident-responsibility policy, avoiding $260-per-unit contractor lock changes
  • Documented close-out with a deficiency list for follow-up and a record for next year’s program

Skills Applied

  • Project Planning & Scheduling
  • Resource & Capacity Planning
  • Budget Review & Cost Control
  • Vendor Coordination
  • Stakeholder Communication
  • Progress Tracking
  • Issue Logging & Resolution
  • Project Close-out