Project Coordination
Annual in-suite HVAC maintenance across 300 units

- Role
- Project Coordinator (Condo Administrator)
- Timeline
- Annual project · 5-day delivery window
Overview
Coordinated the building’s annual in-suite fan coil filter replacement and HVAC maintenance program for a 300-unit residential condominium in downtown Toronto. Suite entry was required in every home, so the project depended on budget approval, clear communication with 600+ residents, controlled access, and close daily tracking with the HVAC vendor to finish within a five-day window. Every unit that couldn’t be accessed as scheduled meant a return visit costing the corporation more than $200 in vendor charges plus a two-hour minimum for a security escort, so first-time access was the main driver of cost and schedule.
Project at a Glance
- Scope
- 300 suites, 600+ residents
- Schedule
- 5 days, ~60 units (five floors) a day
- Daily crew
- 2 vendor technicians + 1 security escort
- Cost of a missed unit
- $200+ per return visit (2-hour minimum at $120/hr plus travel and materials), plus a security escort at a 2-hour minimum ($28/hr + tax)
Project Goals
- Make sure all 600+ residents knew the suite-entry schedule and how to prepare
- Complete the work in all 300 units within five days
- Track progress daily and keep the project on schedule
- Keep regular communication with the HVAC company’s Project Manager
- Identify and resolve issues or delays as quickly as possible
Key Activities
- Obtained the work order and quotation from the vendor, reviewed costs against the corporation’s approved budget, and secured approval from the Property Manager and Board Treasurer
- Built the schedule around daily capacity: two technicians and one security escort completing about 60 units (five floors) a day
- Sent electronic suite-entry notices to all residents with a preparation checklist (clear access to fan coil units, arrange care for pets)
- Posted hard-copy notices in the elevators, mailroom, lobby and front desk so every resident received the information
- Arranged security escorts for technicians entering suites when residents were not home, following the building’s access procedures
- Tracked daily progress with the HVAC Project Manager: technicians on site, floors and units completed, and units that could not be accessed
- Logged every access issue and its cause (resident illness, blocked units, locks changed without notifying Management) for follow-up and future planning
- Minimized return visits, each costing $200+ in vendor charges plus a two-hour minimum security escort, through clear preparation checklists and early follow-up with residents
- Grouped any return visits (up to five a day) to make the best use of vendor and security time
- Stated in resident notices that residents who changed their locks must provide access, so the corporation didn’t pay the $260-per-unit cost of a contractor lock change
- Obtained the final report from the HVAC Project Manager and documented outstanding deficiencies and units needing return visits
Outcomes
- All 300 units completed within the planned five-day schedule (~60 units a day)
- 600+ residents informed through digital and physical notices, with minimal disruption
- Fewer than 10 of 300 units needed a return visit (about 97% completed on the first visit), avoiding $200+ in vendor costs plus security time for each unit accessed the first time
- Locked-suite access handled under resident-responsibility policy, avoiding $260-per-unit contractor lock changes
- Documented close-out with a deficiency list for follow-up and a record for next year’s program
Skills Applied
- Project Planning & Scheduling
- Resource & Capacity Planning
- Budget Review & Cost Control
- Vendor Coordination
- Stakeholder Communication
- Progress Tracking
- Issue Logging & Resolution
- Project Close-out