Project Coordination
Coordinating a building-wide service program across 300 client accounts

- Role
- Administrator (project coordination)
- Timeline
- Annual program · 5-day delivery window
Overview
Coordinated the annual building-wide maintenance program for 300 client accounts in a high-volume downtown Toronto building. Every space required scheduled entry, so the project depended on budget approval, clear communication with 600+ clients, controlled access, and close daily tracking with the vendor to finish within a five-day window. Getting into each space the first time was the main driver of both cost and schedule.
Project at a Glance
- Scope
- 300 client accounts, 600+ clients
- Schedule
- 5 days, about 60 accounts a day
- Daily crew
- 2 vendor technicians + 1 security escort
- Stakeholders
- Clients, management, senior leadership, the vendor’s Project Manager and technicians, security
- Cost of a missed visit
- $240+ per follow-up visit (2-hour minimum at $120/hr plus travel and materials), plus a security escort at a 2-hour minimum ($28/hr + tax)
Project Goals
- Make sure all 600+ clients knew the entry schedule and how to prepare
- Complete the work for all 300 accounts within five days
- Track progress daily and keep the project on schedule
- Keep regular communication with the vendor’s Project Manager
- Identify and resolve issues or delays as quickly as possible
Key Activities
- Obtained the work order and quotation from the vendor, reviewed costs against the approved budget, and secured approval from management and senior leadership
- Built the schedule around daily capacity: two technicians and one security escort completing about 60 accounts a day
- Sent electronic entry notices to all clients with a preparation checklist
- Posted hard-copy notices in high-traffic common areas and at the front desk so every client received the information
- Arranged security escorts for technicians entering spaces when clients were not present, following the building’s access procedures
- Tracked daily progress with the vendor’s Project Manager: technicians on site, accounts completed, and spaces that could not be accessed
- Logged every access issue and its cause (client illness, blocked access, locks changed without notifying management) for follow-up and future planning
- Reduced follow-up visits through clear preparation checklists and early follow-up with clients
- Grouped follow-up visits (up to five a day) to make the best use of vendor and security time
- Stated in client notices that clients who had changed their locks must provide access, avoiding a $260 contractor lock change per account
- Obtained the final report from the vendor’s Project Manager and documented outstanding deficiencies and accounts needing follow-up visits
Outcomes
- All 300 accounts completed within the planned five-day schedule (about 60 a day)
- 600+ clients informed through digital and physical notices, with minimal disruption
- Fewer than 10 of 300 accounts needed a follow-up visit (about 97% completed on the first visit), which kept follow-up costs to roughly $3,000 (about $240 in vendor charges plus about $56 for a security escort, before tax, per visit)
- Locked-door access handled under the client-responsibility policy, avoiding $260-per-account contractor lock changes
- Documented close-out with a deficiency list for follow-up and a record for next year’s program
Skills Applied
- Project Planning & Scheduling
- Resource & Capacity Planning
- Budget Review & Cost Control
- Vendor Coordination
- Stakeholder Communication
- Progress Tracking
- Issue Logging & Resolution
- Project Close-out